Waterway Notices / Weir 11, above Bridge 27, Wood Bridge, Nuneaton
Navigation and Towpath Closure beginning 16 November 2026 at 08:00 to 11 December 2026 at 16:00 at Weir 11.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
Summary
| Type | Navigation and Towpath Closure |
| Start Date | 16 November 2026 at 08:00 |
| End Date | 11 December 2026 at 16:00 |
| Start Location | Weir 11 |
| Ends Location | Weir 11 |
Updates
21 September 2026 at 07:15
An additional navigation closure is required to facilitate water leak prevention works.
The works involve the installation of a horseshoe dam, which will temporarily block the navigation and allow the affected section to be dewatered. This will enable approximately 10m² of damaged brickwork to be removed and replaced to seal a breach in the canal wall and prevent further water loss.
We apologise for any inconvenience caused and thank you for your patience while these essential repairs are completed.