Advice beginning 10 August 2026 at 07:00 to 21 September 2026 at 15:00. Starting at Lock 10, Ganny, ending at Flood Lock, Ledgard.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
| Type | Advice |
| Start Date | 10 August 2026 at 07:00 |
| End Date | 21 September 2026 at 15:00 |
| Start Location | Lock 10, Ganny |
| Ends Location | Flood Lock, Ledgard |
Please could boaters be aware that spot dredging is due to start on Monday, 10th August, on the Calder and Hebble Navigation and will continue until Monday, 21st September.
Works are scheduled as follows but dates are subject to change, should delays occur:
Ganny Lock & Red Beck 13/08 - 26/08
Anchor Pit 27/08 - 01/09
Battye Cut End 01/09 - 03/09
Greenwood 03/09 - 08/09
Long Cut End 09/09 - 11/09
Cooper Bridge (Flood gates) 14/09 - 15/09
Ledgard (Flood gates) 17/09 - 18/09
Boating customers may be asked to wait up to 30 minutes for safe passage and/or any equipment to be moved where necessary. All works are intended to improve the channel and clear extensive siltation.