Waterway Notices / Lock 69, Brynich Lock, Brynich, Brecon, Wales

Navigation Closure beginning 9 November 2026 at 08:00 to 27 November 2026 at 16:00. Starting at Bridge 163, Cefn Brynich Bridge, ending at Lock 69, Brynich Lock.

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Summary

TypeNavigation Closure
Start Date9 November 2026 at 08:00
End Date27 November 2026 at 16:00
Start LocationBridge 163, Cefn Brynich Bridge
Ends LocationLock 69, Brynich Lock

Updates

16 July 2026 at 09:40

A navigation closure is required for Leak arrest works on Lock 69 and Bridge 163. The canal will be dewatered for the duration of the works, between Lock 69, Brynich Lock to immediately downstream of Bridge 163 where a dam will be cited. The pounds either side of the Lock 69 and Bridge 163 will not have their water levels adjusted.

There will be a sandbag bund on the Bypass Wier to increase the freeboard height to the weight preventing water from increasing into the work area as a result more water than usual may be witnessed exiting via the nearest weir in the pound above Lock 69 being Llanbrynean Syphon Weir, this is not of concern.