Towpath Restriction beginning 1 June 2026 at 09:18 at Bridge 100, Friarage Bridge.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
Summary
| Type | Towpath Restriction |
| Start Date | 1 June 2026 at 09:18 |
| End Date | Ongoing |
| Start Location | Bridge 100, Friarage Bridge |
| Ends Location | Bridge 100, Friarage Bridge |
Updates
9 September 2026 at 09:52
Since our last update, the Heritage Association approval has been granted for the new handrail, and our team have received the replacement handrail.
Third-party contractors have now scheduled the works and will be attending site from Monday, 14 September to begin the installation. The works are expected to take approximately one week to complete.
Please continue to follow the signage in place and take extra care when passing through the area.
We will provide a further update on or before Thursday, 17 September.
19 August 2026 at 16:11
Access to the towpath from Bridge 100 on the Lancaster Canal is currently restricted due to the installation of scaffolding.
Scaffolding remains in place to maintain safe conditions while we await approval from the Heritage Association for the design of a replacement handrail. Once approval has been received, we will be able to plan the installation of the new handrail.
Please follow the signage in place and take extra care when passing through the area.
We will provide a further update on or before Wednesday, 9 September.
31 July 2026 at 14:07
Access to the offside towpath from Bridge 100 on the Lancaster Canal remains closed while scaffolding is in place to keep the area safe until a replacement handrail can be installed.
Access from the bridge to the nearside towpath remains open and available for use.
Please follow the signage in place and take extra care when passing through the area.
We will provide a further update on or before Friday 21 August.
17 July 2026 at 08:54
The towpath at Bridge 100 on the Lancaster Canal remains closed
Works to repair the towpath are still delayed while we still await approval from the Heritage Association and confirmation of a start date from our contractors.
Please continue to follow the signed diversion route and take extra care when passing through the area.
A further update will be provided on or before Friday 31 July.
3 July 2026 at 14:52
The towpath at Bridge 100 on the Lancaster Canal remains closed
Works to repair the towpath are still delayed while we still await approval from the Heritage Association and confirmation of a start date from our contractors.
Please continue to follow the signed diversion route and take extra care when passing through the area.
We apologise for any inconvenience caused and thank you for your patience.
A further update will be provided on or before Friday 17 2026.
19 June 2026 at 12:53
The towpath at Bridge 100 on the Lancaster Canal remains closed.
Unfortunately, works to repair the towpath have been delayed while we still await approval from the Heritage Association and confirmation of a start date from our contractors.
Please continue to follow the signed diversion route and take extra care when passing through the area.
We apologise for any inconvenience caused and thank you for your patience.
A further update will be provided on or before Friday, 3 July 2026.
5 June 2026 at 08:59
The towpath at Bridge 100 on the Lancaster Canal remains closed.
Repair works have been delayed while we await approval from the Heritage Association and confirmation of a start date from our contractors.
Please follow the signed diversion route and take extra care when passing through the area.
We apologise for any inconvenience caused and thank you for your patience.
A further update will be provided on or before Friday, 19 June 2026.
1 June 2026 at 09:17
The towpath is closed at Bridge 100 on the Lancaster Canal.
This is due to ongoing towpath repair works
Please follow the signed diversion route and take care when travelling through the area.
A further update will be provided on or before Friday, 5 June 2026.