Customer Service Facility beginning 15 December 2025 at 15:01 to 24 March 2026 at 15:48 at Pump Out, Coventry Br1 S1 mooring.

This notice has ended and is no longer active.

Summary

TypeCustomer Service Facility
Start Date15 December 2025 at 15:01
End Date24 March 2026 at 15:48
Start LocationPump Out, Coventry Br1 S1 mooring
Ends LocationPump Out, Coventry Br1 S1 mooring

Updates

11 March 2026 at 12:31

Works to complete the installation of a new suction line and ducting are due to be completed week commencing 16th March.

We will advise further during week commencing 23rd March.

4 March 2026 at 16:06

Due to unforeseen circumstances we have not been able to get an update from our contractors.

We will update the notice as soon as we know more.

16 February 2026 at 11:14

A quotation has now been approved, documentation and permits to dig are now being produced and we are awaiting a start date from our contractors. A further update will be provided Monday 2nd March.

5 February 2026 at 10:50

Works to replace the failed hose line are now being arranged.

An further update will be provided Monday 16th February.

22 January 2026 at 11:14

Our pump contractors are in the process of sorting hoses required to hopefully sort the problem on site. They believe a supplier has been sourced and are looking at how soon they can have these delivered.

An update will follow as soon as we have more information on an install date.

15 January 2026 at 10:50

It has still not been possible to fix the issue on site. Our contractors are liaising with a more specialist team in their organisation in order to progress this repair.

Another update will be posted when more information becomes available.

7 January 2026 at 16:06

Our contractors attended yesterday 6th January, however due to the weather conditions were not able to do anything, as the equipment was all frozen up.

They will need to revisit once the weather conditions improve.

A further update will be posted regarding this as soon as we know more.

24 December 2025 at 10:53

We were expecting a dual contractor visit this morning, but unfortunately, due to circumstances beyond our control, this has not been possible.

We have requested both contractors advise a new date, but this will not be possible until the new year due to the Christmas and New Year holidays.

We will post a further update in the new year, apologies for the delayed repair.

19 December 2025 at 15:21

Please be advised that the pump-out facility remains out of action.

We are currently awaiting a repair timeframe from our contractors and will update this notice as soon as further information becomes available.

15 December 2025 at 15:06

The pump out only is out of order due to lack of any power.

Please bear with us whilst our contractors attend.