Customer Service Facility beginning 9 December 2025 at 12:00 to 20 March 2026 at 08:36 at Hillmorton CSF.

This notice has ended and is no longer active.

Summary

TypeCustomer Service Facility
Start Date9 December 2025 at 12:00
End Date20 March 2026 at 08:36
Start LocationHillmorton CSF
Ends LocationHillmorton CSF

Updates

26 February 2026 at 17:11

Construction of the new accessible toilet has been temporarily suspended. Work on the new Elsan and water point facility is continuing as planned and these will be completed shortly.

We will provide a further update once a confirmed timeframe is available. Thank you for your patience.

16 December 2025 at 11:18

We are expecting the new facility to be ready for use by 27 February 2026, subject to any unforeseen delays. A further update will be provided once confirmation is received.

9 December 2025 at 12:06

Please be advised that the Elsan at Hillmorton is currently out of service due to the installation of a new facility.

The nearest alternative Elsan disposal points are:

  • Boughton Road (OX-021-011)
  • Braunston (OX-036-004)

We appreciate your patience and understanding during this period. A further update will be provided once a completion date for the new facility is confirmed.