Waterway Notices / Advice - Sheffield & South Yorkshire Nav, Upstream of Rotherham Forge Island Weir, Rotherham

Advice beginning 8 December 2025 at 08:00 at Tesco Accomodation Bridge.

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Summary

TypeAdvice
Start Date8 December 2025 at 08:00
End DateOngoing
Start LocationTesco Accomodation Bridge
Ends LocationTesco Accomodation Bridge

Updates

28 July 2026 at 08:47

We have been advised by the contractors that these works have been extended due to the discovery of a protected species in the area. They are currently awaiting guidance from Natural England before they proceed any further.

This notice will be updated once we have more information.

16 July 2026 at 11:12

Contractors have advised that works to repair the river wall are still ongoing and should be completed by Friday, 24th July.

Should a further extension be required, this notice will be updated as soon as possible.

14 May 2026 at 15:33

Contractors have advised that the piling works have been completed and the works to repair the river wall wall will be in progress till the 14th of July.

28 November 2025 at 09:08

Piling works will begin within a former car parking area adjacent to the spur which leads to the weir at Forge Island. The works are part of a Rotherham MBC scheme to develop the car park into a public amenity space.