Waterway Notices / Bridge 37A (St Mary’s Road) Leamington Spa
Towpath Restriction beginning 31 October 2025 at 16:00 to 11 November 2025 at 16:00 at Bridge 37A, St Marys Road.
This notice has ended and is no longer active.
Summary
| Type | Towpath Restriction |
| Start Date | 31 October 2025 at 16:00 |
| End Date | 11 November 2025 at 16:00 |
| Start Location | Bridge 37A, St Marys Road |
| Ends Location | Bridge 37A, St Marys Road |
Updates
7 November 2025 at 09:10
Our reactive team will be on site on Monday and Tuesday to carry out works to make the bank safe again. Please take care if passing through the area in the meantime.
31 October 2025 at 16:06
Part of the bank has collapsed into the canal near Bridge 37A (St Mary's Road). Navigation remains unaffected, but please take extra care if passing along the towpath and keep to the towpath side.
Hazard tape has been placed around the affected area, and our engineer will be inspecting the site to plan necessary repairs.