Landscaping works Between Bridge 31 Oblique Bridge and Bridge 30 Granary Bridge, Primrose Hill

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Detail

TypeAdvice
Start Date8/25/2025, 7:00:00 AM
End Date11/21/2025, 5:00:00 PM
Start LocationBridge 31, Oblique Bridge
Ends LocationBridge 29, Grays Inn Bridge

Updates

22 July 2025 at 12:25

Contractors Blakedown Landscapes SE Ltd will be carrying out landscaping works close to the canal on the offside.

Please approach with caution and follow any signs or instructions from the contractor.

The works are expected to take 14 weeks.

Moorings will be suspended on the offside during the works.

The navigation and towpath will remain open during the works but approach the area with caution.