Pipe Bridge 4B - Fossdyke Canal

This notice is archived and no longer active.

Detail

TypeNavigation Restriction
Start Date2/19/2024, 12:00:00 AM
End Date2/13/2024, 4:02:26 PM
Start LocationBridge 4B, Pipe Bridge
Ends LocationBridge 4B, Pipe Bridge
Towpath ClosedNo

Description

Third party contractors, Alfred Bagnalls & Sons on behalf of Cadent, will be carrying out remedial works to the overhead Gas Pipe at Bridge 4B, Burton Meadows, West of Lincoln City on the Fossdyke canal. These works are taking place between 19th February and 24th June.

Scaffolding needs to be erected over the navigation. Works methodology and access requires the use of a mobile floating pontoon & craft for transporting materials.

Delays of up to 30 minutes can be expected for passing craft to allow contractors to move pontoon if restricting navigation. Passing craft to navigate the works location slowly, with caution and in single file.

The contactors will provide towpath banksman to manage the passage of towpath users whilst the scaffold is being erected.

Updates

Third party contractors, Alfred Bagnalls & Sons on behalf of Cadent, have postponed these works until later in the year.