Replacement of off-side canal wall with sheet piling
This notice is archived and no longer active.
Detail
From Date: | 29/01/2024 07:00 |
To Date: | 19/04/2024 18:00 inclusive |
Type: | Advice |
Reason: | 3rd Party Works |
Is the towpath closed? | No |
Description
Works are to dredge the canal bed to 1.2m depth, install sheet piling with back piles, backfill with concrete, install brick coper & recycled plastic fender. Silt curtain to be installed during dredging.
Closest waterway: | Grand Union Canal |
Starts at: | Bridge 200B, Gwr Bridge |
Ends at: | Bridge 200C, Nestles Bridge |