Passage through Haddlesey Lock is not possible due to the closure at Beal Lock,
We are awaiting contractors to confirm when works can start to remove the flood debris & silt,
We will update the notice when a date has been confirmed.
Updates
The Dredging team have now completed works at Beal lock and the navigation is now open.
4/4/2024The dredging team have been on site at Beal lock all week unfortunately they have been unable to remove enough of the significant amount the flood and siltation deposit for the lock to be operational, therefore navigation will have to remain closed.
The team will be returning Tuesday 2nd April, we will update this notice when works are complete.
3/28/2024The dredging team have been on site at Beal lock all week unfortunately they have been unable to remove enough of the significant amount the flood and siltation deposit for the lock to be operational, therefore navigation will have to remain closed.
The team will be returning Tuesday 2nd March, we will update this notice when works are complete.
3/28/2024Works are progressing well at Beal Lock, we are hoping dredging will be completed for the Easter Holiday,
We will update this notice no later than 4pm Thursday 28th March.
3/26/2024Due to rising river levels the dredging mobilisation at Beal lock has been delayed. Mobilisation will now commence on 21st March 2024, providing river levels have returned to normal levels.
We anticipate these works will take between 12-14 days to complete, river levels depending.
Everything that can be done to complete these works sooner and enable passage at Easter is being explored.
3/21/2024Contractors are due to start works to remove the flood and siltation deposit at Beal Lock week commencing 4th March, we are anticipating this to be completed by the 15th March.