Notice Archive /

Between Vines Park Barge Lock and Lock 6, Droitwich Junction

This notice is archived and no longer active.

Detail

TypeAdvice
Start Date1/24/2024, 1:00:00 PM
End Date3/25/2024, 11:00:00 AM
Start LocationBarge Lock
Ends LocationBridge 20, Barge Lock Swing Bridge
Towpath ClosedNo

Description

Please be advised we've had to close this section due to an excessive build-up of silt. Passage should not be attempted until further notice. The dredging team have been made aware and will prioritise works accordingly.

A further update will be provided on or before Wednesday 7th February.

Updates

We're pleased to advise contractors have made great progress and navigation will be open again from tomorrow (21/03/24)

Please be advised that dredging plant may still be working in the area, from Lock 6 to M5 crossing, up to Monday 25/03/24. Please take care if passing.

3/20/2024

Contractors are getting ready to mobilise over the next week with the aim is to have navigation open in time for Easter.

Updates to follow as soon as they become available.

3/6/2024

Navigation remains closed here. We're still aiming to have navigation open for Easter. An update will be provided on or before Wednesday 6th March.

2/29/2024

A site meeting was held between the Trust and contractors, mapping the areas that require the spot dredging. We don't currently have a date for when works will commence, but we're aiming to have navigation open for Easter.

The next update will be provided on or before Wednesday 28th February.

2/7/2024