Notice Archive /

Cowling Swing bridge No. 191, located approx 1km west of Silsden, West Yorkshire

This notice is archived and no longer active.

Detail

TypeNavigation Closure
Start Date2/12/2024, 8:00:00 AM
End Date2/29/2024, 4:00:00 PM
Start LocationBridge 191, Cowling Swing Bridge
Ends LocationBridge 191, Cowling Swing Bridge
Towpath ClosedYes

Description

We would like to advise you of this additional stoppage to the Winter Works Programme.

Due to the size of the lifting operation, we will be using a contract lift to remove Cowling bridge (191) and replacing it with a new bridge.

We have explored the option of doing this work as a restriction but unfortunately due to the nature of the works, involving heavy lifting and large cranage, we need to do a canal closure to ensure the safety of customers and those working on site.

This means the navigation will be closed from 14 February 2024 through to 27 February 2024.

Updates

After the initial investigation into this work, contractors have informed us that they need an extension of 4 days to remove the bridge, prepare the foundations and install the new bridge.

This means the start date of the closure will now be the 12 February 2024 and the completion date will be the 29 February 2024.

1/16/2024