Gringley Lock- Upstream Towpath Side Paddle
This notice is archived and no longer active.
Detail
Type | Advice |
Start Date | 9/20/2021, 1:15:00 PM |
End Date | 11/18/2024, 12:00:00 AM |
Start Location | Lock 61, Gringley Lock |
Ends Location | Lock 61, Gringley Lock |
Towpath Closed | No |
Description
The upstream towpath side paddle at Lock 61, Gringley Lock is out of order, therefore skippers of all craft are advised to use the offside lock paddle.
Repair works are being planned in to resolve the issue and once a date has been confirmed this notice will be updated accordingly.
Apologies for any inconvenience this may cause.
Updates
The blockage in the culvert has partially freed and the paddle is operable, though not at full capacity.
A dewater will still be required to clear the remaining blockage.
5/11/2023Passage through the lock is possible using the upstream offside ground paddle.
We will be carrying out further investigations on the upstream towpath ground paddle culvert. We believe the culvert is obstructed, contractors are attending in early February to undertake a survey.
Apologies for inconvenience caused during these works.
1/27/2022Divers have completed their investigations today.
Unfortunately it was not possible to carry out a full repair, and passage through the lock is not possible.
Further investigations are required and we will update this notice as soon as a date is confirmed for these further works.
We apologise for any inconvenience.
1/25/2022