Advice beginning 17 July 2026 at 06:30 to 17 July 2026 at 16:00 at Lock 2, Hawley Lock.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
| Type | Advice |
| Start Date | 17 July 2026 at 06:30 |
| End Date | 17 July 2026 at 16:00 |
| Start Location | Lock 2, Hawley Lock |
| Ends Location | Lock 2, Hawley Lock |
The Reactive Team will carry out welding repairs to the split mitre posts on both the top and bottom gates to temporarily stabilise the gates until permanent replacement works are undertaken.
The works will involve welding steel strengthening plates to the mitre post areas.
During the welding activities, it is likely that navigation will need to be temporarily stopped to ensure the safety of passing boats and the workforce.
Navigation will reopen as soon as it is safe to do so following completion of the welding operations.
Please stop and wait when instructed by the Canal & River Trust team.