Towpath Restriction beginning 1 July 2026 at 07:00 to 25 September 2026 at 16:00. Starting at Bridge 29, Grays Inn Bridge, ending at Bridge 31, Oblique Bridge.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
| Type | Towpath Restriction |
| Start Date | 1 July 2026 at 07:00 |
| End Date | 25 September 2026 at 16:00 |
| Start Location | Bridge 29, Grays Inn Bridge |
| Ends Location | Bridge 31, Oblique Bridge |
A new pedestrian footbridge connecting Camley Street and Granary Street is to be constructed over the canal under a winter works stoppage (currently in consultation).
To prepare for the bridge being lifted into place the Contractor Ardmore require a towpath closure for 12 weeks so that they can install wall supporting props to ensure the brick wall along the back edge of the towpath remains stable during bridge abutment piling works.
The pontoon towpath diversion is approximately 35 metres long near the access point west of Camley Street.
There will be a towpath closure in place for 35 metres in length with a pedestrian/cycle pontoon diversion alongside the towpath. Moorings in the location of the pontoon will be suspended.
A Mooring suspension will be in place from 1/7/26 to 25/9/26 (24 hours 7 days a week).