Navigation Closure beginning 28 April 2026 at 14:00. Starting at Lock 1, Top Lock Rushall, ending at Rushall Junction Bridge.
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
| Type | Navigation Closure |
| Start Date | 28 April 2026 at 14:00 |
| End Date | Ongoing |
| Start Location | Lock 1, Top Lock Rushall |
| Ends Location | Rushall Junction Bridge |
Navigation on the Rushall Lock Flight remains closed due to complications arising from planned works currently being undertaken in the mile pound between Lock 2 and Lock 3.
Our team has now recommenced works on site and progress is back on track. Further updates will be provided as work continues, with the next update expected by Tuesday.
We have had to close navigation on the Rushall Lock Flight due to complications arising from planned works currently being undertaken by our team in the mile pound between Lock 2 and Lock 3.
As part of these works, four courses of brickwork have been removed from the canal wall. To protect the integrity of the embankment and prevent water levels rising above the remaining brickwork, the water level in the mile pound has been lowered. As a result, boats are unable to proceed through the Rushall Lock Flight until further notice.
Our team will attend site tomorrow to assess the situation further. We will provide a further update by Thursday.