Notice Archive / Railway Bridge, Witton

Advice Notice from 10 March 2026 at 08:00 to 11 March 2026 at 17:00. Starting at Railway Bridge, Witton, ending at Railway Bridge, Witton.

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Summary

TypeAdvice
Start Date10 March 2026 at 08:00
End Date11 March 2026 at 17:00
Start LocationRailway Bridge, Witton
Ends LocationRailway Bridge, Witton

Updates

5 March 2026 at 09:31

Third-party inspection works will be carried out at Witton Railway Bridge on the Tame Valley Canal.

The inspection is to be undertaken from within the watercourse by inspectors in drysuits.

Signage is to be placed both upstream and downstream of the works and banksmen are to be in place to notify boaters and communicate to the inspection team of any boat traffic.

Map