Navigation Restriction beginning 31 January 2026 at 22:00 to 8 March 2026 at 06:00 at Bridge 4C, Gas Pipe Bridge.
This notice is archived and no longer active.
| Type | Navigation Restriction |
| Start Date | 31 January 2026 at 22:00 |
| End Date | 8 March 2026 at 06:00 |
| Start Location | Bridge 4C, Gas Pipe Bridge |
| Ends Location | Bridge 4C, Gas Pipe Bridge |
IES Utilities Group are undertaking the removal of a redundant gas pipe and bridge spanning the Fossdyke Canal and adjacent Railway at Bridge 4C, Gas Pipe Bridge, Skellingthorpe. This work will be undertaken between the 31st January 2026 and 8th March 2026 from 10 pm to 6 am. There will be restrictions on the following dates to move materials, erect scaffolding, lift the bridge and pipework.
The towpath and navigation will remain open during the day, however, there may be delays of up to 20 minutes. Pedestrians may need to be escorted through the works. Please be aware of increased activity in the area.