Rotton Park Junction Turnover Bridge

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Detail

TypeAdvice
Start Date11/14/2025, 7:00:00 AM
End Date12/5/2025, 5:00:00 PM
Start LocationIcknield Port Road Bridge 2
Ends LocationRotton Park Junction Turnover Bridge

Updates

18 November 2025 at 13:39

Third-party contractors were scheduled to install a porta dam in the canal between Rotton Park Junction Turnover Bridge and Icknield Port Road Bridge 2 on 06/10/25 to enable repairs to the canal wall. However, unforeseen issues on site caused a delay to the installation. The porta dam has now been successfully installed and is expected to remain in place until 05/12/25. Warning signs have been erected to manage traffic in the area.

Please follow all signage displayed on site.