Long End Cut flood lock between canal and river, Ravensthorpe

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Detail

TypeNavigation Restriction
Start Date9/22/2025, 7:00:00 AM
End Date10/3/2025, 5:00:00 PM
Start LocationBridge 19, Long Cut End
Ends LocationBridge 28, Pipe Bridge

Updates

5 August 2025 at 15:48

Please could boaters be aware that passage will be restricted due to facilitate Northern Power Grid undertaking overhead line tensioning works to pylon cables as part of the Transpennine Route Upgrade scheme.

Boaters and towpath users may be required to wait up to 20 minutes and should take instruction from banksmen on site.