Navigation Closure Between Bridge 27 Chalk Bridge and Bridge 28 Bleak Hall Bridge (A406), Edmonton
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
Detail
Type | Navigation Closure |
Start Date | 9/1/2025, 7:00:00 AM |
End Date | 1/6/2026, 5:00:00 PM |
Start Location | Bridge 27, Chalk Bridge |
Ends Location | Bridge 28, Bleak Hall Bridge (A406) |
Updates
22 July 2025 at 13:47
Vinci Construction UK Ltd working on behalf of Meridian Water are constructing a new bridge across the navigation.
To carry out the works they will need night time canal stoppages (11pm to 6am) 1/9/25 to 5/9/25 and 8/9/25 to 25/9/25 and 14/11/25 to 6/1/26 and a 24 hour towpath closure 1/9/25 to 25/9/25 and 14/11/25 to 6/1/26.
The navigation and towpath will be closed between the dates as advised in the description.