County Weir.
This notice is archived and no longer active.
Detail
Type | Advice |
Start Date | 7/28/2025, 7:00:00 AM |
End Date | 8/1/2025, 5:00:00 PM |
Start Location | Weir 1, County Weir |
Ends Location | Weir 1, County Weir |
Updates
17 July 2025 at 14:34
Further to the notice below, please be advised that these works have been brought forward to the 28th July 2025.
Contractors Robert Nicholas will be working on behalf of Five Rivers in the river on County Weir to cut a notch (0.3m deep by 1m wide) in the weir board to allow migratory fish through.
A dam will be placed in the water to create a dry working area for the contractor who will access the weir via a pontoon.
The nearby lock will remain open to boaters but please approach with caution and follow any instructions from the contractor.
The works are expected to take 3 to 5 days.
You are welcome to contact us at [email protected] or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.
15 July 2025 at 08:36
Please be advised that contractors Robert Nicholas will be working on behalf of Five Rivers in the river on County Weir to cut a notch (0.3m deep by 1m wide) in the weir board to allow migratory fish through.
A dam will be placed in the water to create a dry working area for the contractor who will access the weir via a pontoon.
The nearby lock will remain open to customers, but please approach with caution and follow any instructions from the contractor.
The works are expected to take 3 to 5 days.
You are welcome to contact us at [email protected] or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.