Sileby Marina, Rothley LE12 7UX
This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.
Detail
Type | Advice |
Start Date | 7/14/2025, 7:00:00 AM |
End Date | 8/12/2025, 5:00:00 PM |
Start Location | Bridge 21C Gas Pipe |
Ends Location | Bridge 21C Gas Pipe |
Updates
28 July 2025 at 09:41
These works were originally due to complete on 3rd August, however, the contractors have asked to extend the completion date to 12th August 2025.
10 July 2025 at 10:38
National Grid Distribution Services are undertaking work to install ducting for an electric cable underneath the River Soar to replace an existing overhead service at Sileby Marina, Rothley https://w3w.co/papers.streak.applause from14th July until 3rd August including weekends between the hours of 8 am and 6 pm.
These works are not expected to affect navigational traffic or towpath users. Please be aware of increased activity in the area.