TypeAdvice
Start Date6/18/2025, 7:00:00 AM
End Date6/18/2025, 4:00:00 PM
Start LocationBridge 22 (Railway)
Ends LocationBridge 22 (Railway)

Description

Network Rail will be placing a propelled pontoon carrying scaffold on to the water to carry out a visual inspection of the underside of the railway bridge. If required Pontoon will be moved to allow passing canal boaters...

Updates

Network Rail will be placing a propelled pontoon carrying scaffold on to the water to carry out a visual inspection of the underside of the railway bridge. If required Pontoon will be moved to allow passing canal boaters. Maximum 20 minute delay. No Towpath closure required.