Detail
| Type | Navigation Restriction |
| Start Date | 6/2/2025, 6:00:00 AM |
| End Date | 6/6/2025, 6:00:00 PM |
| Start Location | Bridge 8, Forge Lane Road Bridge |
| Ends Location | Bridge 8, Forge Lane Road Bridge |
Updates
8 May 2025 at 15:41
Third-party contractors will be onsite at Bridge 8 on the Ashton Canal (Forge Lane Road Bridge) to remove a redundant gas pipe. Works are scheduled to take place from 7AM on Monday 2 June and will be completed by 7PM on Friday 6 June. We kindly ask all customers to approach the area with caution and follow any instructions given by contractors onsite. You may be asked to wait at a safe distance while work is carried out. We do not anticipate any delays lasting longer than 30 minutes.