Lock 36 Otherton, Penkridge

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Detail

TypeNavigation and Towpath Closure
Start Date1/5/2026, 8:00:00 AM
End Date3/13/2026, 4:00:00 PM
Start LocationLittleton Colliery Railway Bridge 80A
Ends LocationBridge 83 Lyne Hill Bridge

Updates

12 September 2025 at 12:30

The gates are composite and after further investigations are going to require off-site refurbishment. We require additional time at this stoppage to complete the works to the necessary standard. Starting the works a bit earlier will allow us to complete by the original 13 March 2026 completion date. 

8 May 2025 at 15:05

A navigation and towpath closure are required for top and bottom gate replacements.