Notice Archive / Lock 36 Otherton, Penkridge

Navigation and Towpath Closure Notice from 5 January 2026 at 08:00 to 13 March 2026 at 16:00. Starting at Littleton Colliery Railway Bridge 80A, ending at Bridge 83 Lyne Hill Bridge.

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Summary

TypeNavigation and Towpath Closure
Start Date5 January 2026 at 08:00
End Date13 March 2026 at 16:00
Start LocationLittleton Colliery Railway Bridge 80A
Ends LocationBridge 83 Lyne Hill Bridge

Updates

12 September 2025 at 12:30

The gates are composite and after further investigations are going to require off-site refurbishment. We require additional time at this stoppage to complete the works to the necessary standard. Starting the works a bit earlier will allow us to complete by the original 13 March 2026 completion date. 

8 May 2025 at 15:05

A navigation and towpath closure are required for top and bottom gate replacements.