Culvert 16, between bridges 22 and 23, Strines

This is a live notice. Please check the Canal & River Trust website for the latest information. View on Canal & River Trust website.

Detail

TypeNavigation and Towpath Closure
Start Date10/27/2025, 8:00:00 AM
End Date1/30/2026, 4:00:00 PM
Start LocationBridge 22, Turf Lea Lift Bridge
Ends LocationBridge 23, Stanley Hall Bridge

Updates

12 December 2025 at 12:59

Following the dewatering of the canal, our engineering team carried out a detailed inspection of the canal bed and washwalls. This revealed that the towpath-side washwall—particularly near the aqueduct—is in significantly poorer condition than originally expected. Sections of the wall are leaning inward, lack proper foundations, and have large voids at the base. To ensure the canal remains safe and watertight, we have had to revise the scope of the repair works. As a result of these essential additional repairs, the current stoppage will need to continue beyond the original end date. We now plan to reopen the canal on Friday 30 January 2026, and the navigation will remain closed throughout the Christmas period. Please note that poor weather conditions may affect progress and could lead to further delays. To help accelerate the programme, two masonry teams are now on site, and weekend working is scheduled throughout December and January. We appreciate your patience and understanding while we complete these important works to protect the canal's long-term integrity. If you have any questions, please feel free to contact us.

21 October 2025 at 07:21

Please be advised that the towpath will be closed from 27th October to allow for the safe mobilisation of plant and equipment ahead of the planned stoppage works at Culvert 16 and Strines Aqueduct.  A clearly signposted diversion route will be in place for towpath users during this period.  Please note: Navigation will remain open until 3rd November, after which it will close until 19th December, in line with the advertised stoppage notice.

8 August 2025 at 14:45

We're currently in the process of reviewing the publication dates for these works, as additional vital repairs have been identified. As a result, we're re-evaluating the time and resources required to complete everything to the highest standard. While we anticipate that the dates may change, we're committed to keeping you updated and will share any revisions as soon as they're confirmed.

29 June 2025 at 20:33

Following a change to the scope of the works, we will now be renewing a 60m length of the canal bed. We will be re-lining the canal bed over Aqueduct 7 (Strines) & Culvert 16 with clay and doing repairs to the masonry wash walls as well as installing new access steps. The canal will need to be dewatered to enable the works, which are planned to control leakage from the canal.

6 May 2025 at 08:51

A navigation and towpath closure are required for canal bed, culvert and wash walls re-lining and re-sealing works over the Aqueduct.