Advice beginning 9 April 2025 at 10:16 to 24 July 2025 at 14:37 at Lock 39, Pigeons Lock.
This notice is archived and no longer active.
| Type | Advice |
| Start Date | 9 April 2025 at 10:16 |
| End Date | 24 July 2025 at 14:37 |
| Start Location | Lock 39, Pigeons Lock |
| Ends Location | Lock 39, Pigeons Lock |
We have identified a large log blocking the offside ground paddle culvert, attempts to dislodge it have been unsuccessful, Our contractor will need to deploy further equipment and resource to hopefully dislodge the obstruction.
For this to be implemented, we've extended this stoppage until the 24th of July.
It is taking longer than usual for the lock to fill due to a blocked ground paddle pipework. Method to clear the blockage are being planned
This notice was originally posted on an old system which has now been upgraded, the original description and latest update have been transferred here. To view any historical updates related to this notice, please click here (link to file).